  • In March of 2010, Enfield Energy LLC and the Town Board signed the Developers’ Agreement (PDF).
  • On November 12, 2014, the Enfield Town Board passed the SEQRA Final Environmental Impact Statement Resolution in regard to the Black Oak Wind Farm.
  • On May 25, 2026, the Enfield Town Board passed the SEQRA Extension Resolution (PDF).
  • On September 28, 2016, the signatures for the petition (PDF) to impose a 90-day moratorium prior to approving a wind energy permit to black oak wind farm was submitted to the Town Clerk