Black Oak Wind Farm
The Black Oak Wind Farm was a proposed onshore wind energy project that was first conceived in 2007, but ultimately cancelled in December 2017. This page serves as an archive of various documents relevant to the project.
Time Lines
The following time lines were composed using documents of Town Board meeting minutes and the Planning Board.
- Black Oak Wind Farm History Long Version (PDF)
- Black Oak Wind Farm History Short Version (PDF)
- Black Oak Wind Farm Letter May 26, 2017 from Enfield Town Board
———————————————–
November 12, 2014 The Enfield Town Board passed the SEQRA Final Environmental Impact Statement Resolution in regard to the Black Oak Wind Farm. Please visit the Black Oak Wind Farm website for the Statement and complete report: http://www.blackoakwindny.com/EIS
SEQRA Extension Resolution passed May 25 2016
Developer’s Agreement
Signatures for Petition to Impose a 90-Day Moratorium Prior to Approving a Wind Energy Permit to Black Oak Wind Farm – Submitted to Town Clerk September 28, 2016:
petition-90-day-moratoriumpetition-90-day-moratorium
Application for Wind Energy Permit 2009:
https://townofenfieldny.gov/application-for-…-enfield-ny-2009
COMMENTS 2016
- FINAL PUBLIC WRITTEN COMMENTS-5-11-16 (2)
- FINAL PUBLIC WRITTEN COMMENTS SECTION 2
- 4-12-16 Public Hearing on BOWF DSEIS Verbatim Transcription
- 2016-March-28-Black-Oak-Wind-Farm-DSEIS- Verbatim Transcription Public-Hearing
SIGNATURE PETITIONS
- signatures-community-residents-for-wind-energy-law-changes-2016
- signatures-shared-proposal-for-wind-energy-law-changes-2016
- signatures-shared-proposal-for-wind-energy-law-changes-2016-more-signatures
- signatures-support-of-wind-farm-part-1
- signatures-support-of-wind-farm-part-2
New York State Environmental Quality Review Act Lead Agency Findings Statement for the Black Oak Wind Farm
HBROC-_2406567-v1-Final_Findings_Statement